BUSINESSES ON WASHINGTON STREET ARE OPEN DURING CONSTRUCTION

Latest Status Update: May 14 to May 27, 2018

WORK DURING THIS TIME PERIOD INCLUDES SIDEWALK, ELECTRICAL, DRAINAGE, MICROGRID, TEMPORARY STRIPING, AND WATER MAIN.

DETAILS INCLUDE:

      • Sidewalk installation at 5th and 6th Street.
      • Signal foundations and Microgrid installation at 5th and 6th Streets.
      • Temporary striping at 5th and 6th Streets.
      • Drainage work at 6th, 8th, and 9th, Streets.
      • Saw-cutting for watermain from 9th Street to 11th Street.
      • Watermain tie-ins and valve installations at 11th, 12th and 13th Streets.
      • Water main work from 12th to 13th Street.
      • Construction layout will continue as necessary to provide the locations of proposed work.

LATEST PROGRESS REPORT: MAY 14, 2018 THROUGH MAY 27, 2018

ACCESS NOW


PROGRESS REPORTS ARCHIVE

An inventory of prior Bi-weekly progress reports can be found below.

LATEST PROGRESS REPORT: APRIL 30, 2018 THROUGH MAY 13, 2018

ACCESS NOW


APRIL 16, 2018 THROUGH APRIL 29, 2018

ACCESS NOW


APRIL 2, 2018 THROUGH APRIL 15, 2018

ACCESS NOW


MARCH 19, 2018 THROUGH APRIL 1, 2018

ACCESS NOW


MARCH 5, 2018 THROUGH MARCH 18, 2018

ACCESS NOW


FEBRUARY 19, 2018 THROUGH MARCH 4, 2018

ACCESS NOW


FEBRUARY 5, 2018 THROUGH FEBRUARY 18, 2018

ACCESS NOW


JANUARY 22, 2018 THROUGH FEBRUARY 4, 2018

ACCESS NOW


JANUARY 8, 2018 THROUGH JANUARY 21, 2018

ACCESS NOW


DECEMBER 11, 2017 THROUGH DECEMBER 24, 2017

ACCESS NOW


DECEMBER 11, 2017 THROUGH DECEMBER 24, 2017

ACCESS NOW


NOVEMBER 27, 2017 THROUGH DECEMBER 10, 2017

ACCESS NOW


NOVEMBER 13, 2017 THROUGH NOVEMBER 26, 2017

ACCESS NOW


OCTOBER 30, 2017 THROUGH NOVEMBER 11, 2017

ACCESS NOW


SEPTEMBER 25, 2017 THROUGH OCTOBER 10, 2017

ACCESS NOW


SEPTEMBER 11, 2017 THROUGH SEPTEMBER 24, 2017

ACCESS NOW


AUGUST 28, 2017 THROUGH SEPTEMBER 10, 2017

ACCESS NOW


AUGUST 14, 2017 THROUGH AUGUST 27, 2017

ACCESS NOW


JULY 31, 2017 THROUGH AUGUST 13, 2017

ACCESS NOW


JULY 17, 2017 THROUGH JULY 30, 2017

ACCESS NOW


JUNE 3, 2017 THROUGH JULY 16, 2017

ACCESS NOW


JUNE 19, 2017 THROUGH JULY 2, 2017

ACCESS NOW


JUNE 5, 2017 THROUGH JUNE 18, 2017

ACCESS NOW


MAY 22, 2017 THROUGH JUNE 4, 2017

ACCESS NOW


MAY 8, 2017 THROUGH MAY 21, 2017

ACCESS NOW


APRIL 24, 2017 THROUGH MAY 7, 2017

ACCESS NOW


APRIL 10, 2017 THROUGH APRIL 23, 2017

ACCESS NOW


MARCH 27, 2017 THROUGH APRIL 9, 2017

ACCESS NOW


MARCH 13, 2017 THROUGH MARCH 26, 2017

ACCESS NOW


FEBRUARY 27, 2017 THROUGH MARCH 12, 2017

ACCESS NOW


FEBRUARY 13, 2017 THROUGH FEBRUARY 26, 2017

ACCESS NOW


JANUARY 16, 2017 THROUGH JANUARY 29, 2017

ACCESS NOW


JANUARY 16, 2017 THROUGH JANUARY 29, 2017

ACCESS NOW


JANUARY 2, 2017 THROUGH JANUARY 15, 2017

ACCESS NOW


DECEMBER 19, 2016 THROUGH JANUARY 1, 2017

ACCESS NOW


DECEMBER 5, 2016 THROUGH DECEMBER 18, 2016

ACCESS NOW