BUSINESSES ON WASHINGTON STREET ARE OPEN DURING CONSTRUCTION

Latest Status Update: June 19, 2017 through July 2, 2017

WORK DURING THIS TIME PERIOD INCLUDES WATER MAIN, MICROGRID, SAW CUTTING, FLUSHING OF MAIN, DRAINAGE, AND THE INSTALLATION OF WATER SERVICES.

DETAILS INCLUDE:

  • Water Service Installation from 2nd to 5th, and fire services from 1st to 4th.
  • Saw cutting and removal of existing curb and installation of new curbing at Newark and 1st Street intersections.
  • Drainage installation at Newark and 1st Street intersections.
  • Microgrid work will continue from Newark to 5th Street.
  • Construction layout will continue as necessary to provide the locations of proposed work.
  • Two-way traffic flow will be maintained on Washington.

LATEST PROGRESS REPORT: JUNE 19, 2017 THROUGH JULY 2, 2017

ACCESS NOW


PROGRESS REPORTS ARCHIVE

An inventory of prior Bi-weekly progress reports can be found below.

JUNE 5, 2017 THROUGH JUNE 18, 2017

ACCESS NOW


MAY 22, 2017 THROUGH JUNE 4, 2017

ACCESS NOW


MAY 8, 2017 THROUGH MAY 21, 2017

ACCESS NOW


APRIL 24, 2017 THROUGH MAY 7, 2017

ACCESS NOW


APRIL 10, 2017 THROUGH APRIL 23, 2017

ACCESS NOW


MARCH 27, 2017 THROUGH APRIL 9, 2017

ACCESS NOW


MARCH 13, 2017 THROUGH MARCH 26, 2017

ACCESS NOW


FEBRUARY 27, 2017 THROUGH MARCH 12, 2017

ACCESS NOW


FEBRUARY 13, 2017 THROUGH FEBRUARY 26, 2017

ACCESS NOW


JANUARY 16, 2017 THROUGH JANUARY 29, 2017

ACCESS NOW


JANUARY 16, 2017 THROUGH JANUARY 29, 2017

ACCESS NOW


JANUARY 2, 2017 THROUGH JANUARY 15, 2017

ACCESS NOW


DECEMBER 19, 2016 THROUGH JANUARY 1, 2017

ACCESS NOW


DECEMBER 5, 2016 THROUGH DECEMBER 18, 2016

ACCESS NOW