At the April 5, 2017 Council Meeting a project extension of 60 days from Notice of Award was approved for the Contractor. The Notice of Award was November 22, 2016. As a result of the extension, the Contractor must now complete all work on the Project by August 21st, 2018.

Liquidated damages for failure to meet these deadlines are $5,000/day plus $150/hour for engineering and inspection costs. The City shall deduct and retain any money due until completion and acceptance of work.

CONSTRUCTION SCHEDULE FOR SECOND QUARTER 2018
TASK APRIL 2018 MAY 2018 JUNE 2018
Water Main Installation Continues Through April
Continues through 9th Street
Continues Through May
Continues 10th Street
Continues Through June
Continues 11th Street
Water Service Installation Continues through April
Continues through 7th Street
Continues through May
Continues 8th – 9th Street
Continues through June
Continues 9th -10th Street
Underground Electrical (for Microgrid & Traffic Signals) & Drainage Continues through April
Microgrid – Conduit run between Manhole structures previously installed 1st Quarter Drainage – continues with 5th & 6th Street
Continues through May
Microgrid – Conduit run between Manhole structures previously installed 1st Quarter
Drainage – continues with 8th through 10th Street
Continues through June
Microgrid – Conduit run between Manhole structures previously installed 1st Quarter
Drainage – continues with 11th through 13th Street
Traffic Signals Signal foundation installation at 5th & 6th Street Signal foundation installation at 8th & 9th Street Signal foundation installation at 10th & 11th Street
Concrete Work (Curb, Corner Sidewalk, and light pole foundations) 5th Street, weather permitting 6th & 8th Street, weather permitting 9th – 10th Street, weather permitting
Paving Paving between 1st & 5th Street No Paving Scheduled No Paving Scheduled