At the July 11, 2018 Council Meeting, a project extension of 29 days was approved for the Contractor resulting in a new contract completion date of September 21, 2018.

Liquidated damages for failure to meet these deadlines are $5,000/day plus $150/hour for engineering and inspection costs. The City shall deduct and retain any money due until completion and acceptance of work.

CONSTRUCTION SCHEDULE FOR THIRD QUARTER 2018
TASK JULY 2018 AUGUST 2018 SEPTEMBER 2018
Water Main Installation All Water Main has been installed. UUC to focus on tie-in connections between 9th and 14th Street. All Water Main has been installed. UUC to focus on tie-in connections between 9th and 14th Street. All Water Main has been installed. UUC to focus on tie-in connections between 9th and 14th Street.
Water Service Installation Continues through July Continues through 9th – 10th Street. Continues through August Continues through 10th – 11th Street. Continues through August Continues through 10th – 11th Street
Underground Electrical (for Microgrid & Traffic Signals) & Drainage Microgrid – Conduit run and branch connections between Manhole structures installed between 7th and 9th St. Drainage – continues with 9th & 10th Street. Microgrid – Conduit run and branch connections between Manhole structures installed between 10th and 12th St. Drainage – continues with 11th & 12th Street. Microgrid – Conduit run and branch connections between Manhole structures installed between 13th and 14th St. Drainage – continues with 13th & 14th Street.
Traffic Signals Signal foundation installation at 8th & 9th Street. Signal foundation installation at 9th & 10th Street. Signal foundation installation at 11th & 12th Street.
Concrete Work (Curb, Corner Sidewalk, and light pole foundations) 8th and 9th Street, weather permitting. 10th & 11th Street, weather permitting. 12th – 13th Street, weather permitting.
Paving Paving is scheduled to begin on July 30, just south of 5th and conclude just south of 8th Street. Paving scheduled through August 3. No Paving Scheduled