At the July 11, 2018 Council Meeting, a project extension of 29 days was approved for the Contractor resulting in a new contract completion date of September 21, 2018.

Liquidated damages for failure to meet these deadlines are $5,000/day plus $150/hour for engineering and inspection costs. The City shall deduct and retain any money due until completion and acceptance of work.

CONSTRUCTION SCHEDULE FOR FOURTH QUARTER 2018

Please check back by the end of this week for the Q4 Schedule.

TASK OCTOBER 2018 NOVEMBER 2018 DECEMBER 2018
Water Main & Tie-In Installation Water Main COMPLETE through project limits. Water Main Tie-In at 11th, 12th & 14th Street Remain. Water Main COMPLETE through project limits. Water Main Tie-In at 11th, 12th & 14th Street Remain. Water Main COMPLETE through project limits. Water Main Tie-In anticipated COMPLETE by November 2018.
Water Service Installation Domestic Potable Service – COMPLETE. Fire Service – One (1) Remains. Anticipate all service COMPLETE by October 2018. Anticipate all service COMPLETE by October 2018.
Underground Electrical (for Microgrid & Traffic Signals) & Drainage Microgrid – Main conduit run and branch connections between 9th and 10th St. Drainage – Continues with 12th Street drainage, 11th &13th St to follow. Microgrid – Main conduit run and branch connections between 11th and 12th St. Drainage – Continues with 11th & 13th Street. Microgrid – Main conduit and branch connections between Manhole structures installed between 13th. Drainage – continues with 13th.
Traffic Signals Signal foundation installation at 10th& 12th Street. Signal foundation installation at 11th & 12th Street. Signal foundation installation at 11th & 13th Street.
Concrete Work (Curb, Corner Sidewalk, and light pole foundations) 10th & 12th Street, weather permitting. 12th & 14th Street, weather permitting. 11th & 13th Street, weather permitting.
Paving Paving south of 8th St. to south of 11th St. Tentative for 10/22-10/26, weather permitting. No Paving Scheduled. No Paving Scheduled.